Building: Major Renovation
Location: 2200 West Grand Boulevard
Project Cost: $9.2Million
Design Builder: Jenkins Granger LLC, 49% Detroit-Headquartered Firm
Architect: Resendes Design Group
Construction Start: Summer 2010
Construction Completed: Winter 2011
School Highlights: The $9.2 million renovation project at Northwestern High School was completed in 2012. Two light wells were created to brighten the hallways and common areas with skylight atriums. Lighting upgrades were also installed in the conservatory, hallways and classrooms. Additional renovations include new paint and floor tiles in the hallways and large lecture hall on the third floor.