Mumford High School
Building: New Construction
Location: 17525 Wyoming Street
Project Cost: $52.1 million
Square Footage: 239,000SF
Design Builder: White / Turner, 50% Detroit-headquartered joint venture
Architect: Hamilton Anderson Associates
Construction Started: Fall 2010
School Open: Fall 2012
School Highlights
The new $52.1 million Mumford High School is being built on Mumford’s campus athletic field. The school is the largest construction project in the bond program and will accommodate more than 1,500 students when it opens in fall 2012. The new 239,900-square-foot high school will be a LEED Silver Certified state-of-the-art facility and will offer academic core areas, a high-tech media center, modern science laboratories, a courtyard student quad, and a community health clinic.
Click here for a downloandable PDF of this page.
Click here for renderings of the new Mumford High School!
Take a look at these meeting notes for more information!
Mumford High School Meeting Notes, October 2011
Mumford High School Project Update Q & A
Project Activity to-date:
- Safety fencing going up
- Application for foundation and underground utilities submitted to city officials for review
Construction Bid Details